Client
Mylan Germany GmbH
Location
Troisdorf
Services
Turnkey Contractor Services (LPH 3–8)
Overall project management, project oversight, construction management
Laboratory (Safety Level S1)
area
approx. 1.954 m² GFA
approx. 3.700 m³ GV
Construction Costs
approx. € 1.30 million net
Project Term
October 2018 – July 2019
Construction period
February 2019 - July 2019
CP Bauteam carried out the renovation of an existing building for Mylan GmbH, converting it into modern quality control laboratory spaces. As part of the project, office spaces were converted into laboratory areas, and the building’s technical systems and fire protection measures were comprehensively upgraded. The work was carried out while operations continued, requiring precise construction scheduling to ensure that the adjacent laboratory and office areas remained fully operational at all times.