Client
Mylan Germany GmbH
Location
Troisdorf
Services
Turnkey Contractor Services (LPH 2–8)
Overall project management, project oversight, construction management
Laboratory (Safety Level S2)
area
approx. 1.954 m² GFA
approx. 3.700 m³ GV
Construction Costs
approx. € 1.30 million net
Project Term
October 2018 – July 2019
Construction period
February 2019 - July 2019
For Mylan, CP Bauteam converted an existing office and administration building in Troisdorf into modern quality control laboratory facilities. The project was carried out while the building remained operational and included the conversion of office space into laboratories, the adaptation of the building services systems, and the implementation of a new fire safety concept featuring an external steel staircase as a secondary means of escape.