Construction site update

The screed was laid in all areas.

The ventilation system was transported to the 1st floor by crane via a prepared roof opening.

The drywalls are in the closing phase. While the fire protection walls are already closed on both sides, the planking of the remaining walls is being carried out step by step.

Work on the cooling and drinking water pipes is continuing in parallel.